1.0 Purpose
1.1 To lay down a procedure for dispensing of raw material as per the requirement from production department.
2.0 Scope
2.1
This SOP shall be applicable for all raw materials,
which are dispensed for production at NAME” Pharmaceuticals Ltd.
3.0 Responsibility
3.1 Only trained operator is responsible for weighing and dispensing of Raw Material. He/ She also maintains logbook.
3.2 Sr.
Officer, Production/ Production Officer and QA Officer is responsible for
monitoring of receiving and dispensing of raw materials.
3.3 Store In-Charge and Production In-Charge is responsible for proper execution
of the SOP.
3.4 Head of Quality Assurance, Monitoring
the system of compliance.
4.0 Abbreviations and Definitions
4.1 SOP - Standard Operating
Procedure
4.2 FIFO – First In First Out
5.0 Materials and Equipment
5.1 None
6.0 Precaution / Health and Safety Considerations
6.1 Ensure room condition (Temperature, Relative Humidity and cleanness) is OK according to the BMR.
6.2 Calibrate and check the function of the
balance before start up dispensing and record the data in “Daily
Balance Check Log Book”
6.3 Always keep the materials on pallet.
6.4 Use separate utensils for different raw
materials.
6.5 Dispense
the API after dispensing of all other excipients.
6.6 Ensure that the external surfaces of the
containers are dust free.
6.7 Estimate the quantity spilled during
dispensing and record in “Waste Disposal
Logbook”
7.0 Procedure
7.1 Production
department shall give material requisition sheet as per batch manufacturing
record well in advance to stores department.
7.2 After
getting material requisition sheet from production dept. store person shall
check the availability of approved material as per respective batch.
7.3 If any
material found is still lying in under test, the store person shall inform to
Q.C. Immediately Store person shall transfer all the approved materials as per
FIFO system at dispensing area.
7.4 Store
person shall check and verify all the detail, Material name and code, approved
label, Batch No. Mfg. Date and Retest date [use before date] before dispensing.
7.5 Store
person shall check the dispensing area for its cleanliness, temperature and
relative humidity of Dispensing Room before starting dispensing.
7.6 Remove
all previous materials and documents from the Dispensing Room before receiving
materials.
7.7 After
getting Line clearance from QA department, store person shall put ‘On the RLAF of
Dispensing Booth for 15 minutes before starting the dispensing activity.
7.8 After
getting line clearance from QA person, take the materials to Dispensing booth
and start the dispensing activity in presence of production person and store person.
7.9 Production
person shall check the temperature and relative humidity and verify once again
all the detail on the container.
7.10 If any
discrepancy is found, it should bring to the notice of the Head of QA and
necessary action is to be taken as per the instructions.
7.11 Place the container/ polythene bag on the balance in which
materials to be taken. Then press the ‘TARE’ button to make tare zero.
7.12 Open the bulk container/ bag under Laminar Air Flow Hood
and scoop the material into the empty container/ polythene bag.
7.13 Check the weight of each material against the BMR during
weighing.
7.14 Write the factor (if any), actual quantity, and QC Ref. No.
before dispensing each quantity of a material, then sign the BMR and Dispensing
Logbook after dispensing.
7.15 If a material of more than one QC Ref. No (so more than one
factor) dispensed, QA Officer will check it physically and sign in BMR during
dispensing.
7.16 Seal the polythene bag having dispensed materials properly
with cable tie and fixed dispensing label (Annexure-II).
7.17 Use separate clean utensils for each raw material.
7.18 After dispensing all materials take in container and fixed
the label of “DISPENSED MATERIALS”. (Annexure-I)
7.19 Remove and tear off all the labels (‘APPROVED’, ‘SAMPLED’
etc.) of each empty container.
7.20 Store
person shall clean scoops for each Excipients to avoid cross contamination and
shall use separate scoop to avoid cross contamination.
7.21 Fix “TO BE CLEANED” label at all used
equipment inside the room and Room.
7.22 Clean
the area according to the respective SOP.
8.0 Reference Document
8.1 WHO GMP Guideline, trs-986, annex-2
8.2 In-house
9.0 Annexure
9.1 Annexure-I : Label of “DISPENSED MATERIALS”
9.2 Annexure-II : "Dispensing Label”
10.0 Revision History
Version No. |
Brief Reason for the Revision |
Effective Date |
Remarks |
01. |
New |
|
- |
|
|
|
|
11.0 Training
11.1
Training is required for store officer, Production Officer and Quality
Assurance Officer; trained by Head
of Quality Assurance.
Annexure-I : Label of “DISPENSED MATERIALS”
Address
READY
FOR PROCESSING
|