1.0           Purpose

1.1            To define a standard operation procedure of Tablet Compression Machine

 

2.0           Scope

2.1         This Sop is applicable for operation of Tablet Compression Machine of tablet manufacturing area at "NAME"  Pharmaceuticals Ltd.

 

3.0           Responsibility

3.1            Only concern operator is responsible for normal operation. He/ She inform the supervisor about any deviation from normal operation. He also maintains log book.

3.2            Sr. Officer- Production/Officer- Production is responsible for monitoring day to day activity.

3.3            Production Officer and Quality Assurance Officer should ensure that the procedure is implemented properly.

 

4.0           Abbreviations and Definitions

4.1            Not Appreciable

 

5.0           Materials and Equipment

5.1            Tablet Compression Machine

 

6.0           Precaution / Health and Safety Considerations

6.1            Do not run the machine under power without all guards being fixed in correct position.

6.2            Keep the isolator switch to ‘OFF’ position while moving the hand wheel.

6.3            Never rotate the machine backwards when the punches are in position.

6.4            Keep the safety guards closed when the machine is in operation.

6.5            Do not put your hand inside machine when the machine is in operation.

 

7.0           Procedure

7.1           Instruction

7.1.1       Ensure that all lubricators are filled to the correct level.

7.1.2       Ensure that the upper and lower punches are moving freely. At the first sign of sluggishness stop the machine, remove the upper and lower punches, clean and lubricate it with grease.

7.1.3       Ensure isolator switch on the wall is in ‘OFF’ position and oil cup valves closed during break time.

7.1.4       Regulate the speed of the machine only when the motor is running.

7.1.5       Ensure tablet thickness control is set to maximum before fitting punches.

7.1.6       Ensure that the lower punch anti turning plugs are fitted and are working correctly.

7.1.7       When the punches and dies are fitted, do not run the machine without granules unless the pressure adjusting wheel is completely released. Failure to this would cause damage to the punch faces.

7.1.8       Always use die locating bush at the time of fitting dies.

7.1.9       Do not apply much force at the time of tightening the die holding screw. Too much force may crack            the die table.

 

7.2           Operation

7.2.1      Before starting operation, the operators and the production personnel with this operation must ensure that the room is properly cleaned and all materials of previous product are removed.

7.2.2      Examine Machine for cleanliness including rinse water result, dust-extraction unit and area.

7.2.3      Check punches and dies cleanliness.

7.2.4      Rotate hand wheel and check that turrets rotates freely.

7.2.5      Check that pressure wheels are free and pressure is released.

7.2.6      Checked that sockets of upper/lower punches and dies are properly cleaned.

7.2.7      Fit dies using die rod. Ensure that die is fitted in turret, Tighten die holding screws.

7.2.8      Fit lower punches using thin coat of Food Grade Oil on punch barrel. Ensure that punches are       freely moving by pushing the punch tips through the die and allowing the punches to drop back   freely on its own weight. Tighten lower punches with plugs using anti turning strip.

7.2.9      Rotate hand wheel and check that all lower punches moves freely fit upper punches.

7.2.10    Close lower punch guard covers and fit the feed frame check the clearance with turret.

7.2.11    Fix hopper in such way, so as to give 3-5 mm clearance from turret for free flow of granules to the feed frame.

7.2.12    Rotate hand wheel and check that machine is free.

7.2.13    Fit the acrylic guard. Check the condition of oil cups for any spillage of oil, which may contaminate the product. Clean if necessary.

7.2.14    Before starting the operation production person get the line clearance from QA person and affix the status label with Product Name, batch details to equipment.

7.2.15    Load granules in hopper and rotate machine by hand to fill feed frame and dies.

7.2.16    Apply pressure just to form tablet. Check weight of the tablet. Further increase the pressure to       produce required thickness of the tablet.

7.2.17    After completion the operation, to stop the machine (push the red button).

7.2.18    Affix the “To be Cleaned” label and keep the record in Machine Logbook (Annexure-I).

 

8.0           Reference Document

8.1         In-house

 

9.0           Annexure

9.1         Annexure-I         : Format of ‘Machine Logbook’


10.0        Revision History

 

 

Revision No.

Brief reason for the revision

   Effective Date

   Remarks

01

New

 

 

 

 

11.0        Training

11.1       Head of Production or his nominee give the training of production operator and worker.

 

 

 